The Challenge

The bottler's existing line required extensive manual retooling every time production switched between bottle sizes, costing several hours of downtime per changeover and limiting the number of SKUs they could realistically schedule in a week.

Our Solution

We retrofitted the filling, capping, and labeling stations with quick-change tooling and recipe-based HMI controls, allowing operators to switch formats through a guided on-screen sequence instead of manual adjustment.

Sample content for review: client name and figures on this page are placeholders — replace with the verified project details before publishing.

Results

68%

Reduction in changeover time

+22%

Increase in weekly line throughput

4 weeks

From install to full production ramp